Wallaya Residence Nai Harn: foundations nearly complete, 2 units left on the summer offer.
Construction: as of August 25, the most complex stage, foundations and underground structures, is being completed. In Building B, retaining walls are 45% ready, and the underground portion is 75% complete. In September the developer moves on to the first floor of Buildings B and C, with each subsequent floor taking about a month and a half.
Offer: of the 10 units on summer terms, 2 remain. Payment scheme: 50% first payment, then 50% one year after receiving the keys, just two payments total, 0% interest.