Construction at AYANA Soluna Villas continued through August, with work progressing across multiple villas — from structural work to finishing and landscaping.
- Villa No. 43 (Type C) — 98% complete, closest to handover
- Villas 15, 16 and 19 (Type B) — 73%
- Villas 32 and 36 — 72%; Villas 20 and 35 — 67-68%
- Villas 28, 29, 38 and 40 — 61-64%
The communal area is 27% complete, with beams, wall structures and floor slabs currently underway.