The Title Adora Rawai: 59% Complete

Piling and structural works are nearly finished, architectural works underway

59% Complete

The Title Adora Rawai: 59% Complete

Construction of The Title Adora Rawai in Rawai is on schedule. As of September 2026, the project's overall completion has reached 59%.

Piling works are 100% complete, and the structural works are at 96%. Architectural works are at 34%, and installation of engineering systems (MEP) is at 43%.