October 9, 2026

Gardens of Eden construction progressing on schedule

Fresh construction update: windows, masonry and pile works are progressing on schedule across three Gardens of Eden projects

Construction progress

Gardens of Eden construction progressing on schedule

Developer Gardens of Eden has shared a construction update for September–October 2026, covering all three complexes at once.

  • At Eden Residences (Layan), buildings G, E, F, C and D have completed window installation on the 3rd floor and started on the 4th floor; building A is gaining height, with the 2nd floor slab now poured.
  • At Park Residences (Bang Tao), buildings H, I, J, K have completed monolithic works and moved on to brickwork and finishing.
  • At Lake Residences (Bang Tao), pile works in buildings T, U, V are 90% complete and nearing finish.

We'll send you the current availability plan and share the latest purchase terms.

Post in our Telegram channel @buroth

Get the current price list and floor plans

Prices and availability change every week — we’ll send the latest price list for this project on WhatsApp. Our service is free for you.

WhatsApp
We reply in 10 minWhatsApp →